Information on this page is for customers in
{{ town-name }}
Sudbury to Hudson Transmission Reliability Project
Why Are We Doing This Project?
This new,115-kilovolt (kV) transmission line is one of a group of projects designed to improve the reliability of the electric system serving the Greater Boston area, both today and in the future.
Where Is This Work Being Done?
The new line was constructed between the Eversource substation in Sudbury, and the Hudson Light and Power substation in Hudson. The new transmission line was energized in December, 2024. Construction was completed November 2024 and restoration will be finalized in 2025.
The approved route included 7.6 miles of underground line within an existing, inactive Massachusetts Bay Transportation Authority (MBTA) railroad corridor, passing through Sudbury, Marlborough, Stow and Hudson. The remaining 1.4 miles of line was built under streets in Hudson.
We are working closely with the Massachusetts Department of Conservation and Recreation (DCR) to co-locate compatible uses within the existing, inactive MBTA corridor. We conducted the civil work and bridge replacement to prepare the site, installed the new transmission line and left a compacted gravel sub-base to support the Massachusetts Central Rail Trail (MCRT). DCR will pave the trail, install safe road crossings and complete final restoration of this publicly accessible shared-use path. Construction on the shared-use path will be completed in 2025.

* View the interactive project map
Traffic management and Rail Trail access
Working in consultation with town officials, we developed Traffic Management Plans (TMPs) for construction of the project.
The TMPs include conditions specific to routing by the EFSB in its decision, a detailed site plan showing underground line location, hours of construction, and area-specific traffic controls. All TMPs are subject to change and may be updated. Due to size, TMPs may take extra time to open/download.
When Is The Work Being Done?
- Filed Environmental Notification Form for review under the Massachusetts Environmental Policy Act (MEPA): May 15, 2017
- Received Certificate of the Secretary of Energy and Environmental Affairs on the Final Environmental Impact Report (FEIR): September 14, 2018
- Filed siting petition with the EFSB: April 20, 2017
- EFSB public hearings: May 25 and June 1, 2017
- Received EFSB approval: December 17, 2019
- Start of construction: Fourth quarter 2022
- Projected in-service date: December 2024
About this project
- Route length: 9 miles
- Line voltage: 115,000-volt (115-kV) transmission line
- Siting review: Massachusetts Energy Facilities Siting Board (EFSB)
Construction Updates
We're committed to keeping neighbors, businesses and community members informed on project activities. This work will not interrupt your electrical service.
We placed the transmission line in-service before the end of 2024, which concluded our portion of the work in the corridor outside of targeted restoration efforts.
We will turn over work in the inactive MBTA corridor to the Massachusetts Department of Conservation and Recreation (DCR) in 2025 who will install the new shared use rail trail.
Sudbury
There are no further activities planned at this time. Additional restoration activities will be completed in spring of 2025.
Hudson
There are no further activities planned at this time. Road restoration will be completed by the town of Hudson in 2025.
Siting and Environmental Notification Form Review
The EFSB Petition Filing is part of the siting regulatory review process for an electric transmission line project. On December 17, 2019, we received approval from the EFSB to construct the Sudbury to Hudson Reliability Project. The Massachusetts Supreme Judicial Court upheld the decision on June 25, 2021.
The EFSB's docket is available for viewing in the organization’s file room. Our filing is docket number EFSB17-02.
On May 15, 2017, we submitted an Environmental Notification Form (ENF) to the MEPA Office for review. On June 12, 2017, the MEPA Office held a public site tour and scoping session for the project.
On September 14, 2018, we received the Certificate of the Secretary of Energy and Environmental Affairs on the Final Environmental Impact Report (FEIR) for the Sudbury - Hudson Transmission Reliability Project.
For more information on the MEPA process, please visit their website.
Community Outreach
We will maintain an active field outreach presence during construction in case members of the public have questions.
Have Questions?
Keeping the lines of communication open is an important part of our work in your community.
For more information about this project, please call the project information hotline at 1-833-836-0302 or email ProjectInfoMA@eversource.com.